SCS Energy Prince Williams RNG

Once completed, this facility will turn landfill gas into pipeline spec Renewable Natural Gas.

Project Details

Keeley Construction is currently installing the structural steel pipe racks, process and utility piping, and setting all the equipment for a greenfield RNG facility. Once completed, this facility will turn landfill gas into pipeline spec Renewable Natural Gas. Piping consists of both carbon steel and stainless steel from ½” to 24”. The project is located in Manassas, Virginia and is on schedule to be completed on time. The project duration is 10 months of construction. The overall peak manpower will be at approximately 40 craft.