Messer Cooling Tower

Messer-US was in need of a quick turn-around install of a complete cooling tower system to run their upgraded ASU.

Project Details

Messer-US was in need of a quick turn-around install of a complete cooling tower system to run their upgraded ASU.  They previously had a fire that destroyed all components of their existing cooling tower system. Keeley provided a turn-key, tight scheduled turnaround that was completed in 2 months. 

One Major challenge with this project was working all disciplines from Civil, Structural, Mechanical, and I/E at the same time in such a condensed area. Keeley was able to utilize their multi-disciplined craft personnel to overcome the need for over-saturation of manpower to accomplish these items all at the same time. 

Despite being on a tight schedule, Keeley had the compressors ready to accommodate the demand for Messer’s upgraded ASU system on-time and within budget. 

Power in Numbers

2021

Indianapolis, IN